Logan Park is a neighbourhood park for families living in the area. It also serves as a playground for children at the adjacent École des Saints-Anges.
In 2015, École des Saints-Anges was expanded to accommodate a growing number of students. Currently, approximately 400 children attend this school. Because the school's expansion project was built on land occupied by its schoolyard, Logan Park consequently now serves as the school's playground.
The park renovation project will be carried out in partnership with the Centre de services scolaires Marie-Victorin (CSSMV).
Challenges
At the moment, the park has only a few play modules, which are of limited interest to different age groups. Overall, it is inadequately configured and lacks furniture. In addition, the park has a drainage problem that causes significant water accumulation in the spring or after heavy rains and icy surfaces in the winter, making it inaccessible during these periods. Furthermore, its current layout does not allow for optimal use of the park in winter.
Objectives
This renovation project aims to improve the park’s drainage, replace the outdated lighting, reconstruct the paths that are in poor condition and that will be destroyed by the work, build a new tobogganing hill, create a new playground area, add street furniture, replace the sand (which attracts a lot of wasps) with mulch, and plant more trees.
Once completed, the project will allow the park to better serve the needs of the school's children, particularly those aged 0 to 12, and see increased use by local residents.
Renovation plan
The work will primarily be focused on three areas: a new playground, the existing playground, and a tobogganing hill.
Located close to the school, this playground will be able to accommodate approximately 150 children at the same time. The theme chosen for this area will be ‘nature,’ which will be reflected in the colours, decor, and accessories. This area will include:
Zones for circulating and socializing;
A central play area consisting of modules with various functions:
This area will be redeveloped under a ‘nature/play’ theme. In addition to recovering an existing module, we plan to replace the existing 0-5 module and add a four-place swing area:
1 toddler seat
1 parent-child seat
2 adult seats
Tobogganing hill
The park currently has three natural mounds, but they are too small to be used for tobogganing in winter.
The project will see the creation of a high hill (higher than the existing mounds) with a slope for sliding and an area for climbing back up.
Other components
A painted movement pathway will be created in the summer of 2024. This pathway will be composed of colourful shapes painted on the ground that cue children to move in different ways.
Timeline
Design: winter 2023
Tender for play modules: February 2023
Tender for construction: March 2023
Start of construction: summer 2023
End of construction: fall 2023
Opening of the play modules close to the school: fall 2023
Opening of the rest of the park: June 2024
Painting the movement pathway: summer 2024
To learn more
For more information on this project, you can contact the Engineering Office at genie@saint-lambert.ca or 450 672-4444.
News
We invite you to consult this page regularly as we will post frequent updates that will allow you to follow the progress of the work
2024-05-22 - Complete reopening of the park
Work is nearing completion and the park will be fully accessible to users later this week. The safety barriers will be removed and the lawn mowed. Everything will finally be ready for children to enjoy by the end of the school year and during the summer season.
Note that the fences delimiting the flower meadow (an area planted with pollinator-friendly plants) will remain in place while the vegetation grows. Some work to correct deficiencies and excavate a pipe will also take place over the next few weeks, but will not prevent use of the park.
2023-10-06 - Playground opening
Work is progressing well. The Birch playground is now open to children at Saints-Anges elementary school. Work will continue until next spring. Stay tuned for the full reopening!
2023-09-12 - Playground status report
Following a safety inspection by a specialized firm, the Parc Logan playground cannot be opened for the time being, as some modules require minor corrections.
The Town is working with the Centre de services scolaires Marie-Victorin to open the playground as soon as possible, once the corrective work has been completed.
2023-03-08 – Information session
An information session to present this project was held on Wednesday, March 8, at 7:30 p.m. at École des Saints-Anges (126 Logan Street). During the meeting, we presented the key aspects of the project, the plans, and the projected timeline. You can see or review the presentation that was shown during the evening.
Following the presentation to the citizens, please note that some minor elements will be modified to finalize the project, including the height of the tobogganing hill which will be reduced.
Use of cookies on the City of Saint-Lambert website
The site of the city of Saint-Lambert uses cookies to ensure the proper functioning of certain features such as the display of alert banners at the top of the pages of the site and the automatic scrolling to confirmation messages when submitting form. You can accept these cookies to preserve these features or refuse them.